~ Renovation Updates ~

After dragging for so long, renovation finally started. The permit was approved on 11 March 2009 and expected completion date is 08 April 2009. 

Day 1 (11-03-09): 
Hacking work can only be done on 16, 17 and 18 March 2009, so the workers start dismantling the old cabinets.

Day 2 (12-03-09): 
Old pipings were replaced with stainless steel pipes. The cornicles were removed. Basin and W.C were removed.

Day 3 (13-03-09): 
Old wires were removed and the doors were removed too.

Day 4(14-03-09) :
The new wires were laid. We went down to Ubi to choose our toilets' bi-fold doors and our wrought iron grilles.

Day 5 (15-03-09):
We went around to inform neighbours that our renovation is going to start on monday.

Day 6 (16-03-09):
Hacking started. The kitchen, toilets and living room tiles were hacked off.

Day 7 (17-03-09):
Hacking completed and all debris removed.

The after hacking pictures:

Our Living Room

Common toilet

Our kitchen

The enlarged kitchen entrance

Bedroom 1

Bedroom 2

Master bedroom


Day 8 (18-03-09):
Our tiles arrived. Everywhere filled with sands and cements.




Day 9 (19-03-09):
New door frame was in place and the opening above the door was plastered. Toilets were waterproof with first layer.

Day 10 (20-03-09):
Kitchen wall tiles 50% up, common toilet wall tiles laid and master toilet wall tiles in progress. Toilets were waterproof with 2nd layer.